T-Rex
600N (belt version) |
Page 7b[click here for index]


Next from the bag 600NH remove the sub bag 600NH4. Remove the
main shaft from the bag. And open the bag 600NH4A and dump the
contents in your parts bowl. It has a bolt and nut we need now.
Slide the main shaft into the head block. Notice that the main
shaft is smaller on one end. The larger side is the side that
goes into the head block. Rotate the main shaft so the bolt hole
aligns with the bolt holes in the head block. NOTE: On the kit I
built I noticed that one side of the head block is flat at the
bolt hole and the other is countersunk. The instruction book did
not say wether to put the head of the bolt here or the nut. I
installed the bolt so the head was there and the nut was on the
flat side. If I find out differently then I will change this here
in my set of instructions. Install the bolt and nut now.

Next install the mixing base. Notice that there is a short side
and a long side. Install the washout base so the short side is
toward the head.
NOTE: It maybe necessary to align the pins on the head block so
the mixing base slides easily. There should be no resistance. If
you push the washout base all the way against the head block then
let go the base should fall straight to the ground. On the one I
built the pins were not straight. The easiest way to get the pins
aligned is to rotate the head block as in the picture above so
that you see just a little light between the pin and the main
shaft. See the circled area showing the gap between the pin and
the main shaft is parallel. There are two directions you can look
from for each pin. Make sure the pins are parallel as viewed from
all angles. The pins only have to be off just a slight angle to
prevent the washout base from sliding freely.